-Cleaned up area & sealed vent line fitting into IB (#1) Rib
-As with the rest of the ribs I removed clecoes, cleaned up holes & riveted #2 rib, installing rivets wet then sealing over the tail
-Fitted the vent line in position
-Sealed & riveted the IB #1 rib
-Sealed & riveted the T-405 & T-410 brackets, however i had to run the reamer through the holes as I couldn’t get the rivets in, hopefully that wont affect seal
-Installed & torqued vent line onto rib fitting & applied sealant to clip on cap assy
-As with the rest I made a hell of a mess but i’d rather have too much sealant than not enough
Manual Reference: 7-6, 7-7
| Installed | Removed | |
| Rivets Today | 84 | 0 |
| Wing Rivets | 3768 | 75 |
| Fuse Rivets | 165 | 2 |
| Empennage Rivets | 2215 | 49 |
| Total Project Rivets | 6154 | 125 |
| Hours | 3 | |
| Total Hours | 560.5 |