-COMPLETED MY WING STORAGE STAND AND MOVED THE LEFT WING INTO THAT
-MOVED MY RIGHT WING INTO THE CONSTRUCTION STAND

-DRILLED, DEBURRED & DIMPLED THEN RIVETED AILERON GAP FAIRING TO SPAR AND TOP SKIN
***COULDN’T RIVET INBOARD-MOST AILERON GAP FAIRING RIVET DUE TO INTERFERENCE WITH NEW S.B AILERON MOUNT DOUBLERS, EMAILED VANS FOR ASSISTANCE***
—Van’s Response 17-DEC-17 – Install MSP42 pulled (pop) rivet
Manual Reference: 7-9
| Installed | Removed | |
| Rivets Today | 83 | 1 |
| Wing Rivets | 2726 | 56 |
| Total Project Rivets | 4947 | 108 |
| Hours | 4 | |
| Total Hours | 451.5 |